Prepared for the Tuesday,
Prepared by Navy – Layna Goodman,
Gary Simmons and Mark Wicklein
1. Landfill and Land Use Control Repairs/Upgrades
SES-Tech
5 – 10 people
One month between August
and September
This project will involve repairing sections of the Metals
and Palisades Landfills, fencing in Parcel 4, and monitoring wells.
2. Pipeline
Investigation - Cancelled
3. Free-Product Recovery
SES-Tech
2 people
One week a month continuous
through August
The technically practicable
endpoint for product recovery systems has been met for the monitoring wells at
all three sites - NMCB, South of Runway 18-36 and SWMU 62. Recovery trenches endpoints at the last two
sites have not met the endpoint. Therefore,
the Navy will continue free-product recovery on monitoring wells that are
producing measurable quantities until the recovery trenches achieve the practical
endpoint.
4.
OUB-1 Remedial Action
EOD Technology (EODT)
50 to 100 people
June through October
This
project is a munitions clearance of 366 acres at Mount Moffett Sites MM-10F,
MM-10G and MM-10H that remain from the 2004 field season.
5.
OUB-2 Supplemental Remedial
Investigation\Feasibility Study
15 to 30 people
July through September
This project
will fill gaps in data collected during previous field seasons at the 17 OUB-2
sites with further action. Results of
this work will lead to a risk assessment, feasibility study, proposed plan and
ROD (2009\2010).
6.
10 to 15 people
July through August
This project
will complete work remaining at
7.
Munitions Quality Assurance
Battelle
5 to 10 people
May through October
Battelle will
be the Navy’s independent quality assurance contractor for the 2008 field
season. In the past, EOD Tech Div has
performed this duty only for a two week period during active munitions
clearance projects. This year, Battelle
will be on-island for
the entire field season and will be involved in all three
munitions projects: OUB-1, OUB-2 RIFS, and Lake Jean\Rifle Grenade range.
8.
Annual Monitoring & IC
Inspections
SES Tech
7 or 8 people
Three weeks starting early
September
This is
the annual groundwater and landfill monitoring project. The annual
institutional control inspection will be completed during this same time
period.
9.
EOD
2 people
One week in September
This is the annual clearance of
surface munitions from the seawall.