Non-Field Work Performed Since Last RAB Meeting
OUB-1:
Contract awarded to USA Environmental
Project plan development
Contract awarded to EOD Technology
Project plan development
OUB-2:
Rifle Grenade range
Contract awarded to USA Environmental
Project plan development
Supplemental remedial investigation\feasibility study
Contract awarded to USA Environmental
Project plan development
Non-Field Work Planned Between Now and Next RAB
Meeting
OU B-1:
Complete project plans
Prepare after action report
Complete project plans
Prepare after action report
OU B-2:
Complete project plans
Prepare after action report
Supplemental remedial investigation\feasibility study
Complete project plans
Prepare after action report and begin risk assessment