MUNITIONS UPDATE

Prepared for the Tuesday, September 9, 2008 Adak RAB Meeting

Prepared by Navy – Mark Wicklein

 

 

Non-Field Work Performed Since Last RAB Meeting

 

OUB-1:     

Lake Jean

            Project plan completion

Mount Moffett sites (MM-10F, MM-10G and MM-10H)

            Project plan completion

 

OUB-2:     

Rifle Grenade range

            Project plan completion

 

Supplemental remedial investigation\feasibility study

            Project plan completion

                       

 

Non-Field Work Planned Between Now and Next RAB Meeting

 

OU B-1:    

Lake Jean

            Prepare after action report

Mount Moffett sites

            Prepare 2008 field season report (interim)

 

OU B-2:          

Rifle Grenade Range

            Prepare after action report

Supplemental remedial investigation\feasibility study

Develop risk assessment

Develop remedial investigation report

Begin feasibility study report